16th Street - 2014

16th Street Resurfacing Project from Waverly Road to Quarterline Road -
The City of Holland was recently awarded $750,000 in Roads & Risk Reserve Funding by MDOT.  This is a City road improvement project to repave the roadway.  The Holland BPW will also be replacing water main between Country Club Road and Quarterline Road.

UPDATE 10-08-2014 -
On Friday, October 10, 2014, the contractor intends to place top course HMA on the westbound lanes.  This will be echelon paving starting at the east end of the job (Quarterline Road) and proceeding west.
On Saturday, October 11, 2104,  the contractor will pave the eastbound lanes.
Starting on Tuesday morning, October 14, 2014 the contractor will be shutting down Waverly Road at 16th Street.  Waverly Road through traffic will be detoured out onto US-31.  We intend to keep one lane in each direction open on 16th Street.  Motorists using 16th Street should expect delays getting through the Waverly intersection.

Schedules may change based on weather or other unforeseen circumstances.

Start Date:  August 25, 2014
End Date:  October 31, 2014

Public Open  House -
Was held Thursday, July 31, 2014; 4-6 pm
Holland First Assembly of God Church
1331 E 16th Street

Construction Limits -
E 16th Street; Waverly Road to Quarterline Road

Detour Routes -
The intersection of Waverly & E 16th Street may be closed for short times during this project.  East/West traffic will detour via another east/west road.  North/South traffic should detour via US-31.

Contact Information -
Roadway, Storm Water or Sidewalk -  Ben. . . . . . 616.928.2427
Water/Wastewater Concerns -           Dave  . . . .  616.355.1646
Garbage Questions -                          Mary Ann . . 616.355.1335                           
Contractor, 
   Michigan Paving & Materials -         Steve Rookus 616-459-9545
SubContractor, 
   Schippers Excavating -                   Trevor Moelker 616-437-9969             
All other emergencies please call 911.