48th Street, from Regent Boulevard to Lincoln Avenue.
This is a City of Holland project to add a turn lane, minor utility work and resurfacing of the roadway.
Construction Limits - Regent Boulevard, south to 48th Street and east to Lincoln Avenue.
Start Date - June 9, 2011
Completion Date - Mid-August 2011
Phases -
Phase I - Regent Blvd. to Central Ave. June 9 - July 12*
Phase II - Central Ave. to Lincoln Ave. July 5 - August 10
Dates are subject to change due to scope of work, weather, or other circumstances.
*Phase I will reopen (with a base coat of asphalt) between Regent and Central before *MDOT starts their bridge project on July 12th. The last course of asphalt will be installed when the entire project is complete in August.
*MDOT will be be doing work on the US-31 overpass on South Washington Avenue. This is not a City of Holland project. Please click on MDOT link below for information about that work.
Detour Routes -
No through traffic will be allowed. Motorists must follow the posted detour.
Contact Information -
General Project Info - Ben 616-928-2427
Street/Drainage Issues - Brian 616-928-2448
Water/Wastewater Concerns - Joe 355-1518
Refuse or Recycling - Maryanne 355-1330
On-Site Inspector - Doug - 616-292-4836
Life/Property Threatening Emergencies call 911
Contractor -
Brenner Excavating - Jay - 616-291-0664
Open House - An open house was held on Tuesday, March 22, 2011 at the Transportation Service Department.