2019 Waverly Road Construction

This summer Waverly Road will be resurfaced between 16th Street and 48th Streets.  Work will include milling & paving of the road surface, intersection improvements on Waverly south of 24th Street, tracks improvements on Waverly between 40th & 48th Street, as well as track improvements on E 40th between Brooks Avenue and Waverly Road.

Project bids were opened May 3, 2019, with Rieth Riley being the apparent low bidder. 

  • Start Date -  June 20, 2019*
    Revised Start Date - September 23, 2019
    End Date -  September 30, 2019
    Revised End Date - October 31, 2019
     
    *Dates are subject to change due to the scope of work, weather, or other circumstances.

10-11-2019 Update-
Today, (10/11), was a washout due to rain. The contractor has scheduled the final course asphalt on phase 2 for tomorrow (10/12). We will be moving into phase 3 of the project starting next week Monday (10/14).

  • Phase 2 (Southbound Waverly from 32nd to 48th):
    Final course of asphalt 10/12.
    Move traffic control / Open to traffic on 10/14.

    Phase 3 (Northbound Waverly from 32nd to 48th):
    Set up traffic control / Close to traffic on 10/14.
    Removals 10/14, 10/15.
    Milling and base course paving 10/16.
    Adjusting castings 10/17, 10/18.
    Final course of asphalt 10/19.

    Phase 4 (Northbound Waverly from 32nd to 16th):
    Start phase 10/21 +.
    Weather permitting we will proceed with the final phase of the project. This phase is going to take a little longer prior phases as there is some road widening on the south side of 24th Street that is planned.

    10-01-2019 Update -
    Phase 1 (Southbound Waverly from 16th to 32nd):
    Final course of asphalt Tuesday (10/1).
    Move traffic control / Open to traffic on 10/2.
  • Phase 2 (Southbound Waverly from 32nd to 48th):
    Set up traffic control / Close to traffic on 10/2.
    Removals 10/3, 10/4, 10/5.
    Milling and base course paving 10/7, 10/8.
    Adjusting castings 10/9, 10/10.
    Final course of asphalt 10/11.
    Move traffic control / Open to traffic on 10/12.
  • Phase 3 (Northbound Waverly from 32nd to 48th):
    Start phase 10/14 +.
  • Phase 4 (Northbound Waverly from 32nd to 16th):
    Start phase 10/21 +.

    09-18-2019 Update - 
    The Contractor for the Waverly Road Resurfacing project, Rieth-Riley Construction Company, has reopened their asphalt plant in Zeeland and are planning to get started on the project on Monday, September 23rd. Phasing will be somewhat different than originally planned. Please see attached notice "WaverlyNotice09-18-19" for more information. During the 1st phase of the project, the Contractor will be working on the southbound side of Waverly Road from 16th to 32nd. Northbound Waverly Road will remain open during phase 1. Weather permitting, phase 1 work should complete in about a week. Additional phases will continue in a similar way as shown on the attachment.

48th Street, 32nd Street and 16th Street will remain open to east/west traffic throughout the project. We will not be milling/paving through those intersections. We encourage businesses employees and patrons to use side streets for access whenever possible. For those properties that don’t have side street access, the contractor will maintain access to driveways but there may be delays when the construction operation is crossing the driveway.

Contractor - Milbocker & Son's.
Important Phone Numbers -      
Rieth-Riley contact -  Greg VanTill                                                         616-260-9815
Rieth-Riley contact - John Boven                                                           616-248-0920
Board of Public Works - Dave Cyrus                                                    616-355-1646
City Contact, Aric Thorne                                                                       616-928-2444
Utility Emergencies (24 hr.) please call                                                616-355-150